MANUFACTURED
CAPITAL
MATERIAL
|
Manufactured capital in the mining context relates to the mining and smelting process and how it is conducted, and the assets, which are being mined and beneficiated. It is important to an organisation’s sustainability because its efficient use allows an organisation to be flexible and innovative and increases the speed at which it delivers.
We enhance our manufactured capital by:
- employing our infrastructure, technologies and processes to use our resources most efficiently; and
- devising technology and management systems that reduce our waste and emissions.
Glencore-Merafe Chrome Venture operations
- Rustenburg ferrochrome plant and Tswelopele pelletising and sinter plant
- Boshoek ferrochrome plant and Motswedi pelletising and sinter plant
- Boshoek mine
- Wonderkop ferrochrome plant and Bokamoso pelletising and sinter plant
- Waterval (east and west) and Marikana mines
- Kroondal mine
- Thorncliffe mine
- Lion ferrochrome plant
- Lydenburg ferrochrome plant
- Helena mine
- Magareng mine
KEY POINTS – 2018 |
|||
![]() |
Merafe attributable ferrochrome production 407kt (2017: 395kt) |
1 fatality (2017: 1)No industrial action Improved TRIFR performance of 3.39 (2017: 3.74) |
|
![]() |
Mined chrome ore production up Cost management |
||
Overview
Attributable ferrochrome production increased to a new record high of 407kt during 2018, which is equivalent to installed capacity utilisation of 85%.
A number of annual production records were achieved during 2018, including all time high production levels for the Lion Smelter and the Wonderkop Smelter.
An annual production record was also achieved by the Bokamoso Sinter Plant at the Wonderkop Smelter.
The production performance did not only result in higher volumes, but also resulted in excellent cost performances. The increase in total unit production cost year on year was contained to 9%, despite the significant increase in the reductant consumption price of 23% and the electricity price increase of 5.2%.
Safety
The Venture continues to place maximum focus on safety. Unfortunately, despite this effort, we are sad to report that there was a fatal accident in the operations of the Venture during 2018 as referred to more fully in the report of the CEO and the report of the Chairperson.
A number of safety campaigns have been undertaken since the onset of the Venture in 2004 as part of the ongoing efforts to improve on the safety performance. This was indeed achieved as evident in the graph below where the total recordable injury frequency rate (TRIFR) reduced to levels around 4 over the past few years. See Human capital of this report for a summary of the Venture’s approach and performance in respect of safety and health for 2018.
| Ref. YTD | 2016 | 2017 | 2018 | ||
| FFR | 0.04 | 0.04 | 0.03 | ||
|---|---|---|---|---|---|
| LTIFR | 1.21 | 1.04 | 1.26 | ||
| TRIFR | 4.15 | 3.74 | 3.39 | ||
| DISR | 111.49 | 145.62 | 116.43 |
Eskom
Our furnaces are fully dependent on a reliable and cost effective supply of electricity from Eskom. Following a period where Eskom anticipated excess generation capacity and was trying to promote incremental electricity consumption, the situation has weakened to a point currently where the Utility has been forced to implement load curtailment again.
Lower electricity sales, higher costs of primary energy and large overexpenditures on their new build programme placed enormous pressure on Eskom's financial situation. The Regulator allowed a 5.2% tariff increase on 1 April 2018 for the 2018/19 financial year. NERSA has, however, meanwhile approved an increase of 4.4% in 2019/20 (held for a four year period) under the Regulatory Clearance Account. In addition, Eskom has applied for a 15% increase in tariffs for each of the next three years under MYPD4. For further discussion on Eskom and pricing rates I refer you to the CEO's strategic review.
The benefits to the Venture of investing into energy efficient projects like Lion phases 1&2, Bokamoso and Tswelopele has shown to be extremely significant and the benefits compared to other ferrochrome producers will increase with future electricity price increases.
Chrome ore production
The Chrome mines (including UG2) produced a new record annual total with saleable chrome ore production at 2.4% more than the previous period.
Higher volumes (15.3%) at the UG2 Operations were mainly due to better recoveries achieved and more feed received from external PGM concentrators.
Chrome produced at the Mines in 2018 was 4.7% less than the previous year due to section 54 stoppage (one fatality), Eskom power failures and Plant breakdowns.
From the Resources and Reserves Statement of this report it is clear that the Venture has more than sufficient ore available at the current rate of mining. If inferred reserves set out in the Mineral Resources and Reserves Statement are excluded, the total life of mine is still calculated at more than 30 years.
TRIFR 2004 – 2017
Power and ore consumption efficiencies
MWh per tonne of ferrochrome
Tonnes of ore per tonne of ferrochrome
The Glencore-Merafe Chrome Venture's operations
| Ferrochrome plants |
Capacity | Technology | Mines |
| Western Limb (North West province) | |||
| Wonderkop | 553 000 tpa FeCr |
Bokamoso pelletising and sintering plant using Outotec technology |
Kroondal, Waterval and Marikana |
| 6 furnaces |
Conventional semi-enclosed furnaces | ||
| Rustenburg | 430 000 tpa FeCr |
Tswelopele pelletising and sintering plant using Outotec technology |
Kroondal, Waterval and Marikana |
| 6 furnaces |
Conventional semi-enclosed furnaces | ||
| Boshoek | 240 000 tpa FeCr |
Motswedi pelletising and sintering plant using Outotec technology |
Waterval, Kroondal and Boshoek |
| 2 furnaces |
Enclosed furnaces | ||
| Eastern Limb (Mpumalanga and Limpopo provinces) | |||
| Lydenburg | 396 000 tpa FeCr |
Premus – kilns | Thorncliffe, Helena and Magareng |
| 4 furnaces |
Three enclosed furnaces and one semi-enclosed furnace |
||
| Lion Phase I | 360 000 tpa FeCr |
Premus – kilns | Thorncliffe, Helena and Magareng |
| 2 furnaces |
Enclosed furnaces | ||
| Lion Phase II | 360 000 tpa FeCr |
Premus – kilns | Thorncliffe, Helena and Magareng |
| 2 furnaces |
Enclosed furnaces | ||
The Venture has access to various UG2 plants, in the Western Limb including EPL, Kanana, Kl, K2, K4 and Rowland, and Mototolo in the Eastern Limb.
